September 11, 2012

1st Deck Pour on the new bridge
1st Deck Pour on the new bridge
435 Cubic Yards of concrete will be poured on September 11
435 Cubic Yards of concrete will be poured on September 11
Concrete Pour needs to cure for 10 days
Concrete Pour needs to cure for 10 days
Crews work in unison with machines to pour and smooth out the concrete
Crews work in unison with machines to pour and smooth out the concrete
Despite a chilly wind crews started at 7 to get the first pour done in one day
Despite a chilly wind crews started at 7 to get the first pour done in one day
Machine smoothes out recently poured concrete
Machine smoothes out recently poured concrete
More than 40 concrete trucks will supply material for the first deck pour
More than 40 concrete trucks will supply material for the first deck pour
Strata Crews supply the 435 cubic yards of concrete for the deck pour
Strata Crews supply the 435 cubic yards of concrete for the deck pour
The first deck pour on the 55th Street Bridge happened on 09-11-12
The first deck pour on the 55th Street Bridge happened on 09-11-12
The first deck pour will cover roughly one-third of bridge deck
The first deck pour will cover roughly one-third of bridge deck
Wet burlap being placed atop the newly poured concrete
Wet burlap being placed atop the newly poured concrete
104k of steel will hold the deck and concrete together
104k of steel will hold the deck and concrete together
Crews keep the burlap wet to help the concrete cure properly
Crews keep the burlap wet to help the concrete cure properly
Roughly 435 cubic yards of concrete were poured in one day
Roughly 435 cubic yards of concrete were poured in one day
The green steel will reinforce the concrete and new deck as it cures over the next 10 days