Progress Report

  Home  »  News »  Progress Report
Each week we will highlight some of the progress on the 31st Avenue project. Here is the status update for October 15th. 
  
  • All utility work complete
  • Asphalt paving will be done in the afternoon of 10/15
  • Striping completed in phase 2 
  • Street is open from 13th to far West trailer park access 
The driving public should use caution and pay attention as work continues. Continue to visit the project website at www.MinotRoads.com for more information including status reports and construction maps.
 
 