Each week we will highlight some of the progress on the 31st Avenue project. Here is the status update for September 10th. 
  
  • Mainline curb is complete
  • Roadway pavement from 2nd to east end complete 
  • Sidewalk of 2nd to 6th complete 
  • Water shut down on 2nd tomorrow (9/11) 
  • Sidewalk and bike path done by next week
     

    The driving public should use caution and pay attention as work continues. Continue to visit the project website at www.MinotRoads.com for more information including status reports and construction maps.