Each week we will highlight some of the progress on the 31st Avenue project. Here is the status update for October 1st. 
  
  • Storm sewer is complete
  • Bike paths and sidewalks ready for gravel
  • Seeding tomorrow (10/2) and Saturday (10/3) 
  • Surface mount work
  • Late next week remaining concrete roadway will be complete
The driving public should use caution and pay attention as work continues. Continue to visit the project website at www.MinotRoads.com for more information including status reports and construction maps.
 
 