Each week we will highlight some of the progress on the 31st Avenue project. Here is the status update for September 17th. 
  
  • Completed storm sewer through 2nd and up to South main
  • Water work is complete through 2nd street 
  • Tuesday (9/22) morning Broadway shut down for utility work
  • Concrete work will continue
  • North side of the road and bike path is complete
  • Light poles are set and on and energized


The driving public should use caution and pay attention as work continues. Continue to visit the project website at www.MinotRoads.com for more information including status reports and construction maps.
 
 