Each week we will highlight some of the progress on the 31st Avenue project. Here is the status update for September 24h. 
  
  • All sidewalks are graded, driveways, continuing on boulevard grading with topsoil placement
  • Graveling Saturday and Sunday
  • Paving in phase 2 and 3B completed Thursday (9/24)
  • Streetlights all up and working in phase 2 and 3B 
The driving public should use caution and pay attention as work continues. Continue to visit the project website at www.MinotRoads.com for more information including status reports and construction maps.
 
 