Project Update

Due to increased costs and funding considerations, the City and NDDOT have decided to split this project into two separate projects: 

  • Limits will be from 14th Avenue SW to Burdick Expressway (including the Burdick intersection).  
  • This south project will remain on the schedule for 2025 construction (tentatively). 
  • The alternatives for the south project can be found here, including updated retention pond scenarios. 
  • These alternatives and the recommended Preferred Alternative for the south project (Alternative B with Pond Scenario 4) were presented to and approved by the City Council at the May 6, 2024, regular City Council meeting.
 
Project Map

  • Limits will be from the north side of Burdick Expressway intersection to 2nd Avenue SW. 
  • This north project will be delayed, likely until the 2028 or 2029 construction season. 
  • The alternatives for the north project can be found here, including two new options for the 5th Ave SW & 7th Ave SW intersections that have been developed since the time of the November 2023 public input meeting. 
  • Comments and feedback are welcome on the north project alternatives and options.  However, no decisions will be made on the north project until a later date (TBD). 
north project map
  • City of Minot ND
  • ND Department of Transportation
  • APEX Engineering



Privacy Policy   •   Disclaimer

© Copyright 2025 Apex Engineering Group
Designed and Developed by Odney